Th. Hirilandhoo Council

Goal 1

Harbour and core infrastructure

Advance the harbour, roads and land reclamation.

Goal progress

Targets

  • 01Complete harbour upgrade by end 2026
  • 02Pave all roads by 2028
Average progress of linked projects57%

Linked projects

Projects that deliver this goal.

All projects
  • Ongoing
    Government projects (PSIP)

    Harbour upgrade

    Expanding and upgrading the harbour for vessels and fish landing.

    Progress62%
    Budget
    MVR 38,000,000
    Government PSIP
    Start
    1 March 2025
    Expected end
    31 December 2026
  • Ongoing
    Council projects

    Road paving (phase 2)

    Second phase of island road paving.

    Progress71%
    Budget
    MVR 1,795,000
    Council budget
    Start
    15 June 2026
    Expected end
    15 December 2026
  • Delayed
    Government projects (PSIP)

    25-hectare land reclamation

    Reclamation of 25 hectares with a 1,080 m revetment and an 80 m groyne.

    Progress38%
    Budget
    MVR 104,700,000
    Government PSIP
    Start
    1 June 2025
    Expected end
    30 September 2026

    Overdue by 21 days