25-hectare land reclamation

Reclamation of 25 hectares with a 1,080 m revetment and an 80 m groyne.

DelayedGovernment projects (PSIP)
25-hectare land reclamation

About this project

To ease land scarcity, a 25-hectare reclamation with a 1,080 m revetment and an 80 m groyne was awarded to MTCC.

The contract value is USD 6.79 million (about MVR 104.7 million).

Works are behind the original schedule.

Milestones

  1. Works commenced

    1 June 2025

  2. Revetment 50% complete

    15 March 2026

  3. Reclamation completion (planned)

    30 September 2026

  4. Revised completion (delay)

    31 March 2027

Photo updates

Related notices and tenders

AnnouncementOpen

Applications for land plots

Ref: (IUL)418-ADM/418/2026/017

Submit land applications before 30 November 2026.

Closes in 40 days·

1

Related council decisions

Demo by NotReal